Programs for implementing network-centric warfare (NCW) in the Navy include
the Cooperative Engagement Capability (CEC) and Naval Integrated Fire Control-
Counter Air (NIFC-CA) systems, the IT-21 program, and FORCEnet. A related
program is the Navy-Marine Corps Intranet (NMCI). Congress has expressed concern
for some of these programs, particularly NMCI. This report will be updated as events
warrant.
Network-Centric Warfare
Network-centric warfare (NCW), also known as network-centric operations (NCO),
is a key element of defense transformation. NCW focuses on using computers, high-
speed data links, and networking software to link military personnel, platforms, and
formations into highly integrated local and wide-area networks. Within these networks,
personnel are to share large amounts of information on a rapid and continuous basis. The
Department of Defense (DOD) and the Navy view NCW as a key element of defense
transformation that will dramatically improve combat capability and efficiency.1
Examples of Navy NCW Programs
CEC And NIFC-CA. The Cooperative Engagement Capability (CEC) system
links Navy ships and aircraft operating in a particular area into a single, integrated air-
defense network in which radar data collected by each platform is transmitted on a real-
time (i.e., instantaneous) basis to the other units in the network. Units in the network
share a common, composite, real-time air-defense picture. CEC will permit a ship to


1 For more on NCW, see CRS Report RL32411, Network Centric Warfare: Background and
Oversight Issues for Congress, by Clay Wilson. For more on defense transformation and naval
transformation, see CRS Report RL32238, Defense Transformation: Background and Oversight
Issues for Congress; and CRS Report RS20851, Naval Transformation: Background and Issues
for Congress, both by Ronald O’Rourke.

shoot air-defense missiles at incoming anti-ship missiles that the ship itself cannot see,
using radar targeting data gathered by other units in the network. It will also permit air-
defense missiles fired by one ship to be guided by other ships or aircraft. The Navy wants
to install the system on aircraft carriers, Aegis-equipped cruisers and destroyers, selected
amphibious ships, and E-2C Hawkeye carrier-based airborne early warning aircraft over
the next several years. The system has potential for being extended to include Army and
Air Force systems.
Tests of CEC aboard Navy ships in 1998 revealed significant interoperability (i.e.,
compatibility) problems between CEC’s software and the software of the air-defense
systems on some ships. In response, the Navy undertook a major effort to identify,
understand, and fix the problems. The CEC system, with the new fixes, passed its
technical evaluation (TECHEVAL) testing in February and March 2001 and final
operational evaluation (OPEVAL) testing in April and May 2001.
In 2002, the primary CEC contractor, Raytheon, faced potential competition from
two firms — Lockheed and a small firm called Solipsys — for developing the next
version of CEC, called CEC Block II. Solipsys had devised an alternative technical
approach to CEC, called the Tactical Component Network (TCN). Solipsys entered into
a teaming arrangement with Lockheed to offer TCN to the Navy as the technical approach
for Block II. In late-December 2002, Raytheon announced that it had agreed to purchase
Solipsys. In early-February 2003, Raytheon and Lockheed announced that they had
formed a team to compete for the development of Block II. Some observers expressed
concern that these developments would reduce the Navy’s ability to use competition in
its acquisition strategy for Block II. As an apparent means of preserving competition, the
Navy in mid-2003 announced that it would incorporate open-architecture standards into
Block II divide the Block II development effort into a series of smaller contracts for which
various firms might be able to submit bids. In December 2003, however, the Navy
canceled plans for developing Block II in favor of a new plan for developing a joint-
service successor to Block I.
The conference report (H.Rept. 108-283, page 290) on the FY2004 defense
appropriations act (H.R. 2658/P.L. 108-87) directed the Navy to keep the Appropriations
committees informed on potential changes to the CEC Block II acquisition strategy and
stated that, if the Navy adopts a new acquisition strategy, “the additional funds provided
in this act for CEC Block 2 may be merged with and be available for purposes similar to
the purposes for which appropriated.” The House and Senate Armed Services
Committees, in their reports (H.Rept. 109-89, page 178, and S.Rept. 109-69, pages 108-

109, respectively) on the FY2006 defense authorization bill (H.R. 1815/S. 1042),


expressed satisfaction with the Navy’s efforts to improve interoperability between the
CEC system and other combat direction systems and ended a requirement established in
the conference report (H.Rept. 105-736) on the FY1999 defense authorization act (P.L.

105-261) for the Navy to report to Congress on these efforts on a quarterly basis.


The Naval Integrated Fire Control-Counter Air (NIFC-CA) system is to combine
the CEC system with the E-2D Advanced Hawkeye carrier-based airborne radar and
control system (AWACS) aircraft and the SM-6 version of the ship-based Standard air
defense missile (both now in development) to expand the Navy’s networked air-defense
capabilities out to the full range of the SM-6 missile. Among other things, NIFC-CA will
enable Navy forces at sea to provide overland defense against enemy cruise missiles.



Current Navy plans call for NIFC-CA to be partially deployed in FY2011 and fully
deployed in 2014.2
IT-21. IT-21, which stands for Information Technology for the 21st Century, is the
Navy’s investment strategy for procuring the desktop computers, data links, and
networking software needed to establish an intranet for transmitting tactical and
administrative data within and between Navy ships. The IT-21 network uses commercial,
off-the-shelf (COTS) desktop computers and networking software that provide a
multimedia organizational intranet. The Navy believes IT-21 will improve U.S. naval
warfighting capability and achieve substantial cost reductions by significantly reducing
the time and number of people required to carry out various tactical and administrative
functions. FY2008 funding requested for IT-21 “continues to provide Integrated
Shipboard Network Systems (Increment 1) procurement and installation to achieve a Full
Operational Capability (FOC) for all platforms by FY2011.”3
FORCEnet. FORCEnet is the Navy’s overall approach for linking various
networks that contribute to naval NCW into a single capstone information network for
U.S. naval forces. The Navy has highlighted FORCEnet as being at the center of Sea
Power 21, the Navy’s vision statement for the future. The Navy states that “Undersea
FORCEnet Satellite Communications (SATCOM) FY2008 funding provides the Internet
Protocol (IP) connectivity between Anti-Submarine Warfare (ASW) platforms to conduct
collaborative ASW. Connecting the platforms for collaborative ASW enables sharing of
time critical queuing, classification, and targeting data, provides a means for precluding
blue-on-blue engagement, and ensures rapid positioning of ASW platforms into the best
attack posture to prosecute the threat submarine.”4
Some observers have criticized FORCEnet for being insufficiently defined.5 The
Naval Network Warfare Command issued a functional concept document for FORCEnet
in February 2005, but Navy officials acknowledged at the time that the concept was not
yet adequately defined and stated that an improved version of the document would be
published in 2006.6
The conference report (H.Rept. 107-732) on the FY2003 defense appropriations bill
(H.R. 5010/P.L. 107-248) expressed concern about “the lack of specificity and


2 For discussions of NIFC-CA, see Amy Klamper, “Fire Control,” Sea Power, March 2006,
available online at [http://www.navyleague.org/sea_power/mar06-19.php], and John Ailes,
presentation entitled “Introduction to Naval Integrated Fire Control-Counter Air (NIFC-CA),”
available online at [http://enterprise.spawar.navy.mil/getfile.cfm?contentId=359&type=C]
3 U.S. Department of the Navy, Highlights of the Department of the Navy FY 2008 Budget, p. 3-

15 (i.e., Section 3, page 15).


4 U.S. Department of the Navy, Highlights of the Department of the Navy FY 2008 Budget, p. 3-

15 (i.e., Section 3, page 15).


5 See, for example, Malina Brown, “Van Riper: Navy’s ForceNet Too Broad, Mysterious To Be
Meaningful,” Inside the Navy, Apr. 7, 2003. See also Malina Brown, “Mullen Acknowledges
ForceNet Concept Not Clearly Understood,” Inside the Navy, July 5, 2004.
6 Jason Ma, “Naval Network Warfare Command Issues FORCEnet Concept Document,” Inside
the Navy, Feb. 14, 2005.

documentation on the program,” and directed the Navy to submit a detailed report on it
by May 1, 2003 (page 279). The Senate Appropriations Committee, in its report (S.Rept.
108-87, page 156) on the FY2004 defense appropriations bill (S. 1382), expressed support
for the FORCEnet program but also said it “is concerned that no requirements have been
approved or implemented and that there is duplication of effort, especially in the areas of
experimentation and demonstrations. The Committee directs that the FORCEnet program
establish these requirements, test them within the Navy Warfighting Experimentations
and Demonstrations line (PE0603758N), and release the approved requirements changes
as quickly as possible.”
NMCI. A significant program related to NCW is the Navy-Marine Corps Intranet
(NMCI), which is a corporate-style intranet linking more than 300 Navy and Marine
Corps shore installations. NMCI is to include a total 344,000 computer work stations, or
“seats.” As of January 2006, the Navy had ordered 341,000 seats and fully implemented
about 264,000. The Navy planned to achieve steady-state operation of all NMCI seats
during FY2007. In October 2000, the Navy awarded an industry team led by Electronic
Data Systems (EDS) Corporation an $6.9-billion, five-year contract for installing,
supporting, and periodically upgrading the NMCI. In October 2002, Congress, through
P.L. 107-254, authorized a two-year extension to this contract, which is now worth $8.9
billion. Congress has closely followed the program for several years.
The NMCI implementation effort has experienced a number of challenges and
delays. A 2005 report from DOD’s weapons-testing office identified problems found with
the program in 2003.7 On September 30, 2004, the Navy and EDS restructured the terms
of the NMCI contract to consolidate the number of performance measures and focus on
measuring results rather than implementation steps. User reaction to the system8
reportedly has been mixed. A December 2006 Government Accountability office (GAO)
report on NMCI stated:
NMCI has not met its two strategic goals — to provide information superiority
and to foster innovation via interoperability and shared services. Navy developed a
performance plan in 2000 to measure and report progress towards these goals, but did
not implement it because the program was more focused on deploying seats and
measuring contractor performance against contractually specified incentives than
determining whether the strategic mission outcomes used to justify the program were
met. GAO’s analysis of available performance data, however, showed that the Navy
had met only 3 of 20 performance targets (15 percent) associated with the program’s
goals and nine related performance categories. By not implementing its performance
plan, the Navy has invested, and risks continuing to invest heavily, in a program that
is not subject to effective performance management and has yet to produce expected
results.


7 Jason Ma, “DOT&E Report Identifies NMCI Problem Areas Found During 2003 Test,” Inside
the Navy, Feb. 7, 2005.
8 Navy Marine Corps Intranet Public Affairs, “Eight Percent of Customers Surveyed Satisfied
With NMCI,” Navy Newsstand, Mar. 6, 2007; John Hoellwarth, “After Five Years, NMCI Still
Frustrates,” Defense News, July 17, 2006: 48; John Hoellwarth, “NMCI ‘Unfriendly’ — And
Running Late,” Navy Times, Mar. 27, 2006: 24; Christopher J. Castelli, “Lawmaker With Reserve
Experience Rips ‘Customer Unfriendly’ NMCI,” Inside the Navy, Mar. 20, 2006.

GAO’s analysis also showed that the contractor’s satisfaction of NMCI service
level agreements (contractually specified performance expectations) has been mixed.
Since September 2004, while a significant percentage of agreements have been met
for all types of seats, others have not consistently been met, and still others have
generally not been met. Navy measurement of agreement satisfaction shows that
performance needed to receive contractual incentive payments for the most recent
5-month period was attained for about 55 to 59 percent of all eligible seats, which
represents a significant drop from the previous 9-month period. GAO’s analysis and
the Navy’s measurement of agreement satisfaction illustrate the need for effective
performance management, to include examining agreement satisfaction from multiple
perspectives to target needed corrective actions and program changes.
GAO analysis further showed that NMCI’s three customer groups (end users,
commanders, and network operators) vary in their satisfaction with the program.
More specifically, end user satisfaction surveys indicated that the percent of end users
that met the Navy’s definition of a satisfied user has remained consistently below the
target of 85 percent (latest survey results categorize 74 percent as satisfied). Given
that the Navy’s definition of the term “satisfied” includes many marginally satisfied
and arguably somewhat dissatisfied users, this percentage represents the best case
depiction of end user satisfaction. Survey responses from the other two customer
groups show that both were not satisfied. GAO interviews with customers at
shipyards and air depots also revealed dissatisfaction with NMCI. Without satisfied
customers, the Navy will be challenged in meeting program goals.
To improve customer satisfaction, the Navy identified various initiatives that it
described as completed, under way, or planned. However, the initiatives are not being
guided by a documented plan(s), thus limiting their potential effectiveness. This
means that after investing about 6 years and $3.7 billion, NMCI has yet to meet9
expectations, and whether it will is still unclear.
Department of Defense officials conceded problems with the implementation of
NMCI at a March 28, 2007, hearing before the Terrorism and Unconventional Threats and
Capabilities subcommittee of the House Armed Services Committee.10
Issues for Congress
Potential issues for Congress include the following:
!Is the Navy’s implementation of NMCI adequate? To what degree is the
system achieving its goals?
!Does the Navy have a clear and adequate acquisition strategy for
developing a successor to CEC Block I?
!Is the FORCEnet concept adequately defined?


9 Government Accountability Office, Information Technology[:] DOD Needs to Ensure That
Navy Marine Corps Intranet Program Is Meeting Goals and Satisfying Customers, GAO-07-051,
Dec. 8, 2006.
10 See Mark A. Kellner, “Top DoD Officials Concede NMCI Woes On Hill,” NavyTimes.com,
Mar. 28, 2007.

!Is the Navy taking sufficient actions for preventing, detecting, and
responding to attacks on NCW computer networks?
!Is the Navy taking sufficient steps to provide adequate satellite
bandwidth capacity to support NCW?
!Are Navy efforts to develop new tactics, doctrine, and organizations to
take full advantage of NCW sufficient?
!Has the Navy taken the concept of NCW adequately into account in
planning its future fleet architecture?11
!What effect will implementation of NCW in U.S. and allied navies have
on U.S.-allied naval interoperability?


11 For additional discussion of Navy force-structure planning, see CRS Report RL32665, Navy
Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald
O’Rourke.