Background on NEPA Implementation for Highway Projects: Streamlining the Process

CRS Report for Congress
Background on NEPA Implementation for
Highway Projects: Streamlining the Process
August 6, 2003
Linda G. Luther
Environmental Policy Analyst
Resources, Science, and Industry Division


Congressional Research Service ˜ The Library of Congress

Background on NEPA Implementation for Highway
Projects: Streamlining the Process
Summary
Before a federally funded surface transportation project can proceed, the
Department of Transportation’s (DOT) Federal Highway Administration (FHWA)
must ensure compliance with all local, state, and federal legal requirements regarding
the environment, including the National Environmental Policy Act of 1969 (NEPA,
42 U.S.C. 4321 et seq.). NEPA requires all federal agencies to provide an
Environmental Impact Statement (EIS) for every proposed major federal action
significantly affecting the quality of the environment. Projects with uncertain or
insignificant impacts also require documentation. Such projects either require an
Environmental Assessment (EA) or are categorically excluded from requirements to
prepare an EA or EIS.
In addition to NEPA, any given transportation project may require compliance
with a wide variety of legal requirements, enforceable by multiple agencies. For
example, impacts of a highway project may trigger requirements under the National
Historic Preservation Act (16 U.S.C. 470) or the Clean Water Act (33 U.S.C. 1251).
FHWA regulations require that compliance with all applicable environmental laws,
executive orders, and other legal requirements be documented within the appropriate
NEPA documentation (a concept referred to as the “NEPA umbrella”).
There has been a long-standing perception that high-profile highway
construction projects have been delayed by implementation of NEPA’s requirements.
However, until recently, there was only anecdotal information directly linking the
“NEPA process” to widespread highway project delays. Several studies conducted
by the General Accounting Office and the FHWA have attempted to determine a
distinct connection between NEPA compliance and highway project delays.
In 1998, Congress passed the Transportation Equity Act for the 21st Century
(TEA-21, P.L. 105-178) that reauthorized the federal surface transportation programs
for highways, highway safety, and transit for fiscal years 1998-2003. To address
concerns regarding highway project delays, Congress included Section 1309 in TEA-
21, “Environmental Streamlining,” that required DOT to develop and implement a
“coordinated environmental review process” for projects having a significant impact
on the environment. That process was intended to encourage full and early
participation by all agencies required to participate in a highway project.
Since TEA-21 was enacted, numerous administrative activities have been
undertaken to facilitate streamlining. However, corresponding regulations have not
been finalized. Continued efforts to streamline the NEPA process are expected in
legislation to reauthorize surface transportation programs for fiscal years 2004-2009.
This report provides background on the NEPA process and discusses streamlining
activities to date. It does not cover current debate on streamlining efforts related to
the reauthorization legislation (see CRS Report RL32032, Streamlining
Environmental Reviews of Highway and Transit Projects: Analysis of SAFETEA and
Recent Legislative Activities). This report will be updated when changes to the
NEPA process are in place.



Contents
Overview of the National Environmental Policy Act..................2
The “NEPA Umbrella” and Transportation Projects...................3
Additional Environmental Review Requirements.....................5
Evaluation of Certain Cultural Resources.......................5
Historic Preservation.......................................6
Dredge and Fill Permit Evaluation............................6
Assessment of Threatened and Endangered Species...............7
Consideration of Social, Economic, and Environmental Impacts.....7
Consideration of Executive Order Requirements.................7
Appropriate NEPA Documentation................................8
Documentation Required When Impacts Are Significant...........9
Documentation Required When Impacts are Not Significant.......16
Documentation Required When the Significance of Impacts is Uncertain
...................................................17
Determining NEPA’s Role in Transportation Project Delays...........19
Studies Examining NEPA’s Role in Project Delays..............19
The Transportation Equity Act for the 21st Century .................25
“Streamlining” Provisions of TEA-21.........................25
Administrative Actions to Implement TEA-21..................26
Challenges to Streamlining.....................................29
Establishing a Statutory Environmental Review Process..........29
Establishing Lead Agency Authority..........................30
Establishing a Statute of Limitations..........................31
Delegating Authority to States...............................31
List of Figures
Figure 1. FHWA Projects by Class of Action...........................18
Figure 2. FHWA Project Funding by Class of Action.....................18
List of Tables
Table 1. Laws, Regulations, and Executive Orders Potentially Applicable to the
NEPA Process for Transportation Projects..........................4
Table 2. Potential Types of Environmental Consequences to be Considered for
Transportation Projects........................................13
Table 3. Estimated Time to Complete Federally Funded Highway Projects....20
Table 4. Environmental and Transportation Improvement Stakeholders’ Most-
Frequently Cited Aspects Adding “Undue Time” to Environmental Reviews of
Highway Projects.............................................23



Background on NEPA Implementation for
Highway Projects: Streamlining the Process
Highway projects are generally initiated by state departments of transportation.
Before final design, property acquisition, or construction on a highway project can
proceed (if the project will receive federal funds) the U.S. Department of
Transportation’s (DOT) Federal Highway Administration (FHWA) must ensure
compliance with all applicable state and federal laws regarding protection of the
environment, including the National Environmental Policy Act of 1969 (NEPA, 42
U.S.C. 4321 et seq.). Numerous federal and state agencies have jurisdiction over
these laws and must interact with DOT and local transportation sponsors to
determine the impacts to the environment for particular projects.
There are a multitude of factors that impact the timing of transportation project
delivery. Factors that may cause delay include the state’s project planning and design
process, changes in the state’s funding priorities, construction complexities, local
controversy, or the environmental review process to name a few. In 1998, to address
delays resulting specifically from the completion of environmental reviews, Congress
included “Environmental Streamlining” requirements in Section 1309 of the
Transportation Equity Act of the 21st Century (TEA-21, P.L. 105-178). During the
reauthorization process, states reported to Congress that the numerous federal
environmental approvals and permits needed to build a highway were inefficient and
overly time-consuming. To address these concerns, Congress included Section 1309
in TEA-21. It was intended to better coordinate federal agency involvement in the
NEPA process.
FHWA defines environmental streamlining as the timely delivery of federally-
funded transportation projects, while protecting and enhancing the environment.
Because major transportation projects may be affected by dozens of federal, state,
and local environmental requirements, administered by multiple agencies, improved
interagency cooperation was identified by Congress as a critical element to the
success of environmental streamlining.
This report discusses the steps required to complete the environmental review
process for transportation projects. In particular, it provides an overview of NEPA
requirements, including elements that are unique to transportation projects and that
have been controversial or of concern to stakeholders with regard to streamlining the
process. This report also discusses transportation project delays and their relationship
to the NEPA process, streamlining provisions of TEA-21 and efforts undertaken by
the Administration to implement those provisions, and challenges to further
streamlining efforts.



Overview of the National Environmental Policy Act
In the 1960s, the public was becoming increasingly aware of and concerned
about human impacts on the environment. In response, Congress attempted to
address the impact of federal actions on the environment by enacting the National
Environmental Policy Act of 1969 (NEPA, 42 U.S.C. 4321 et seq.). NEPA requires
all federal agencies to consider the environmental impacts of major proposed federal
actions. It also requires agencies to inform the public that it has indeed considered
environmental concerns in its decision-making process.
To ensure that environmental impacts were considered, before final decisions
were made, NEPA requires federal agencies to provide a detailed statement of
environmental impacts for every proposed major federal action that significantly
affects the quality of the human environment. The “human environment” is defined
as the natural and physical environment and the relationship of people with that
environment.1 The “detailed statement” was subsequently referred to as an
environmental impact statement (EIS) in regulations to implement NEPA.
Projects with less than significant impacts may require a certain level of
documentation. An Environmental Assessment (EA) is required if it is not clear
whether a project will have significant impacts. Projects that do not individually or
cumulatively have a significant social, economic, or environmental effect, and which
FHWA has determined from past experience have no significant impact, are
processed as Categorical Exclusions (CEs). According to the Federal Highway
Administration (FHWA), in 2001 approximately 3% of all highway projects required
an EIS, almost 7% required an EA, and just over 90% were classified as CEs.
Projects requiring an EIS accounted for 9% of the funds allocated by FHWA. While
such projects represent a small portion of the total projects and funds allocated, they
are often high-profile, complex projects that affect sizeable populations.
When conducting an environmental review under NEPA, agencies are not
required to elevate environmental concerns over other considerations. Rather, NEPA
requires only that the agency take a “hard look” at a project’s environmental
consequences before taking action.2 If the adverse environmental effects of the
proposed action are adequately identified and evaluated, the agency is not constrained
by NEPA from deciding that other benefits outweigh the environmental costs.
NEPA also established the Council of Environmental Quality (CEQ) in the
Executive Office of the President. CEQ formally promulgated regulations to
implement NEPA’s environmental review requirements in 1978.3 CEQ further
directed federal agencies to develop their own policies and procedures to implement


1 40 CFR 1508.14
2 The “hard look” requirement was specified by the U.S. Supreme Court in Kleppe v. Sierra
Club, 427 U.S. 390, 410, n. 21 (1976).
3 40 CFR 1500-1508. Note, Executive Order 11991, issued by President Carter in 1977,
amended CEQ responsibilities requiring it to issue regulations to federal agencies that
clarified the procedural provisions of NEPA.

the CEQ regulations.4 FHWA promulgated regulations to implement NEPA
requirements in 1987.5 In addition to its regulations, FHWA has issued a variety of
guidance documents and technical advisories to assist decisionmakers in completing
the NEPA process for transportation projects.6
The “NEPA Umbrella” and Transportation Projects
For any given transportation project, compliance with a wide variety of statutory
and regulatory requirements, enforceable by multiple agencies, may be required.
Depending upon the resources present at a project site, compliance with legal
requirements regarding any of the following may be required for a given
transportation project:
!Natural Resources
!Physical Resources
!Cultural Resources
!Community Impacts
!Special Status Land Use
Laws and executive orders potentially applicable to highway projects are listed
in Table 1.7 In addition to these requirements, there are state and local requirements
and myriad court decisions addressing virtually every element of NEPA
implementation. Under FHWA regulations, compliance with all applicable
environmental laws, executive orders, and other related requirements must be
documented within the appropriate NEPA documentation.8 In effect, FHWA
coordinates compliance with all applicable environmental requirements under the
“NEPA umbrella.” This means that, for any given transportation project, any study,
review, or consultation required by law that is related to the environment should be
conducted within the framework of the NEPA process. It does not mean that NEPA
itself requires compliance with these requirements. Hence, the NEPA process is the
means by which compliance with such requirements is coordinated, documented, and
proven. If, theoretically, the requirement to comply with NEPA were removed,
compliance with each applicable law would still be required.


4 40 CFR 1507.3
5 23 CFR 771
6 The FHWA Office of NEPA Facilitation maintains a website, “NEPA: Project
Development Process,” at [http://www.fhwa.dot.gov/environment/00001.htm], which
includes FHWA’s environmental policy, FHWA Technical Advisories, and a variety of
guidance materials to facilitate compliance with NEPA at all stages of the process.
7 This list is not necessarily exhaustive and does not include local or state legal requirements
potentially applicable to a given highway project. States may also have their own “NEPA”
statute that may substitute or overlap with the federal NEPA requirements.
8 23 CFR 771.133

Table 1. Laws, Regulations, and Executive Orders Potentially
Applicable to the NEPA Process for Transportation Projects
Natural EnvironmentCommunity Impacts (continued)
Emergency Wetlands Resources Act National Flood Insurance Act
Endangered Species Act Public Hearings, 23 U.S.C. 128
Executive Order 11990, Protection of Title VI of the Civil Rights Act
Wetlands Uniform Relocation Assistance and Real
Executive Order 12962, RecreationalProperty Acquisition Act
Fisheries
Executive Order 13112, Invasive Species
Fish and Wildlife Coordination ActCultural Resources
Marine Mammal Protection Act Act for the Preservation of American
Marine Protection Research andAntiquities
Sanctuaries Act Archaeological and Historical Preservation
Migratory Bird Treaty Act Act
Water Bank Act Archeological Resources Protection Act
Wildflowers, Surface Transportation and Department of Transportation Act,
Uniform Relocation Act, Section 130 “Section 4(f)”
Federal-Aid Highway Act, 23 U.S.C. 109,
Physical Environmentsections (h) Economic, Social and
Clean Air Act, as amended Environmental Effects, and (i) Noise
Clean Water Act, as amended Executive Order 11593, Protection and
Comprehensive Environmental Response,Enhancement of Cultural Environment
Compensation, and Liability Act, as(1971)
amended Historic Bridges, Surface Transportation
Federal Insecticide, Fungicide, andand Uniform Relocation Act, Section
Rodenticide Act 123(f)
Federal Land Policy and Management Act Historic Sites and Buildings Act
(Paleontological Resources) National Historic Preservation Act,
Noise Control ActSection 106
Pollution Prevention Act Native American Graves Protection and
Resource Conservation and Recovery Act Repatriation Act
(RCRA), as amended Reservoir Salvage Act
Safe Drinking Water Act, as amended
Solid Waste Disposal Act (see RCRA)
Special Status Land Use
Impacts to Communities or Individuals Coastal Zone Management Act, as
American Indian Religious Freedom Actamended
Emergency Planning and Community Right Coastal Barrier Resources Act
to Know Act Executive Order 11988, Floodplain
Executive Order 12898, EnvironmentalManagement
Justice Flood Disaster Protection Act
Executive Order 13175, Consultation and Land and Water Conservation Fund Act, as
Coordination With Indian Tribalamended, Section 6(f)
Governments National Trails System Act
Farmland Protection Policy Act Rivers and Harbors Appropriations Act, as
Federal Transit Law, nondiscrimination (49amended
U.S.C. 5332) and relocation requirements Wild and Scenic Rivers Act
(49 U.S.C. 5324) Wilderness Act
Source: Table prepared by the Congressional Research Service (CRS) based on data from FHWA and
the California Department of Transportation.
Note: Statues highlighted in bold italics are those most likely to apply to highway projects and to
affect highway project delivery.



Additional Environmental Review Requirements
Congress has included environmental review requirements in statutes in addition
to NEPA. In this case, an “environmental review” refers to the need to show
evidence of formal consideration, evaluation, or analysis of the impacts of a
proposed federal action. Such requirements have been established by Congress to
provide additional protection to certain sensitive resources or communities. For
example, documentation may be required to show that the project has been evaluated
sufficiently to identify potential impacts to minority communities, publicly-owned
parkland, endangered species habitat, wetlands, floodplains, or historic sites.
Following is a summary of laws and executive orders that direct federal agencies
to conduct environmental reviews. This is not an exhaustive list, however; the
requirements listed below are those that have been of particular relevance to
transportation projects and that have received significant attention from stakeholders
in the streamlining debate.
Evaluation of Certain Cultural Resources. “Section 4(f)” of the
Department of Transportation Act of 1966 applies to the use of publicly owned parks9
and recreation areas, and wildlife and waterfowl refuges. It also applies to public
or privately owned historic sites of national, state, or local significance. When a
project uses such resources, a separate “Section 4(f) evaluation” must be prepared
and included with the appropriate NEPA documentation.
Unlike NEPA, the “significance” of impacts to the resource is not necessarily
relevant. Under the law, any use of such a resource for a transportation project is
prohibited unless:
!There is no prudent and feasible alternative to using such land, and
!The project includes all possible planning to minimize harm to land.
To demonstrate that there is no feasible and prudent alternative, the Section 4(f)
evaluation must analyze alternatives and design shifts that avoid the protected
resource. If Section 4(f) land is chosen for use in a project, the evaluation must
demonstrate that the use of identified alternatives would have resulted in unique
problems. “Unique problems” are present when there are truly unusual factors or
when the costs or community disruption reach extraordinary magnitude.10


9 This provision was set forth at section 4(f) of the DOT Act, and printed in the United
States Code (U.S.C.) at 49 U.S.C. 1653(f). A similar provision is found at 23 U.S.C. 138.
In 1983, as part of a general codification of the DOT Act, 49 U.S.C., 1653(f), was formally
repealed and recodified with slightly different language in 49 U.S.C. 303. Given that over
the years, the whole body of provisions, policies, case law, etc., has been collectively
referenced as “section 4(f)” matters, DOT has continued this reference for this regulation.
10 This test of prudent and feasible alternatives was introduced in Citizens to Preserve
Overton Park v. Volpe, 401 U.S. 402 (1971), and subsequently referred to as “Overton Park
Cr iteria.”

Historic Preservation. The National Historic Preservation Act (NHPA, 16
U.S.C. 470), declares a national policy of historic preservation to protect, rehabilitate,
restore, and reuse districts, sites, buildings, structures, and objects significant in
American architecture, history, archaeology, and culture. Section 106 of NHPA
mandates that federal agencies take into account a project’s effect on a property on,
or eligible for inclusion in, the National Register of Historic Places. NHPA does not
mandate preservation of such resources, but requires all federal agencies to consider
the impact of their actions on such properties and seek ways to avoid, minimize or
mitigate adverse impacts.
Section 106 also requires the agency to seek comments on the project from the
Advisory Council on Historic Preservation (ACHP). Under authority granted by
Congress, the ACHP has issued regulations that set forth procedures that explain how
agencies must take into account the effects of their actions on historic properties and11
how the ACHP will comment on those actions.
Section 106 is an integral part of Section 4(f) compliance whenever historic
properties are involved. Section 4(f) requires that the historic site be granted
protection if it is determined to be of local, state, or national significance. The
Section 106 process is the method by which that significance is determined.
While there are similarities between Section 4(f) and Section 106, there are also
important differences between the statutes. Section 106 of NHPA is primarily a
procedural statute that directs all federal agencies, as opposed to just DOT, to
consider project impacts on certain resources. Section 4(f) of the DOT Act
specifically prohibits the use of certain resources, except under extreme conditions,
and only if the project includes all possible planning to minimize harm to the site
resulting from its use.
Dredge and Fill Permit Evaluation. Section 404 of the Clean Water Act
(33 U.S.C. 1344) requires projects that involve the discharge of dredged or fill
material into waters of the United States to obtain a permit from the U.S. Army
Corps of Engineers. As part of the 404 permit evaluation process, the NEPA
documentation must demonstrate that an evaluation of the need for a permit has been
made. Other federal agencies may be involved in the 404 permit evaluation process,
such as the Department of the Interior’s U.S. Fish and Wildlife Service (FWS), the
Department of Commerce’s National Oceanic and Atmospheric Administration
(NOAA) Fisheries (previously named the National Marine Fisheries Service), or the
U.S. Environmental Protection Agency (EPA). EPA is the only agency with the
authority to veto a Corps 404 permit.
If the evaluation process determines that a “Section 404 permit” is needed,
obtaining the permit may take longer than completion of the NEPA process. (This
discussion addresses only the requirement to perform an environmental review to
determine if a Section 404 permit is required, not the subsequent compliance


11 36 C.F.R. 800

requirements with a 404 permit.12 Also, it does not address requirements to comply
with other requirements under the Clean Water Act.)
Assessment of Threatened and Endangered Species. Section 7 of the
Endangered Species Act of 1973 (16 U.S.C. 1536) requires federal agencies to insure
that actions they authorize, fund, or carry out are not likely to jeopardize the
continued existence of threatened or endangered species or result in the destruction
or adverse modification of designated critical habitat for these species. Such efforts
must be undertaken in consultation with the Secretary of the Interior or the Secretary
of Commerce, as appropriate. The FWS and NOAA Fisheries share responsibilities13
for administering the Act.
As part of the Section 7 consultation, a biological assessment is required when
the presence of threatened or endangered animals or plants are suspected to occur in
the vicinity of a project. The assessment must include an inventory of species in the
project area and report the potential for adverse impacts to the FWS or NOAA
Fisheries.
Consideration of Social, Economic, and Environmental Impacts.
The Federal-Aid Highway Act (23 U.S.C. 109(h)), requires that potential adverse
economic, social, and environmental effects of proposed Federal-aid highway
projects are identified and fully considered. The Act also requires that project
locations are fully considered and that final decisions on highway projects are made
in the best overall public interest. To accomplish these requirements, transportation
projects are required to eliminate or minimize the adverse effects of:
!Air, noise, and water pollution;
!Destruction or disruption of man-made and natural resources, aesthetic values,
community cohesion and the availability of public facilities and services;
!Adverse employment effects, and tax and property value losses;
!Injurious displacement of people, businesses and farms; and
!Disruption of desirable community and regional growth.
Compliance with these requirements should be demonstrated in the appropriate
NEPA documentation.
Consideration of Executive Order Requirements. Requirements of
three executive orders may apply to highway projects, with regard to environmental
review. First, Executive Order 12898, issued in 1994, directed every federal agency
to make environmental justice part of its mission by identifying and addressing the
effects of all programs, policies, and activities on “minority populations and low-
income populations.” Two executive orders issued in 1977 directed federal agencies
to avoid, to the extent possible, long and short term adverse impacts to floodplains


12 As specified under 40 CFR 230-233.
13 Regulations governing interagency cooperation under Section 7 are found at 50 CFR 402.

and wetlands.14 Construction on, or modification to, such resources is to be avoided
wherever there is a practical alternative.
Compliance with each of the requirements listed above is required under
separate statutory or Executive authority, apart from NEPA. However, evidence of
compliance with each of these requirements is required by FHWA to be contained
in the appropriate NEPA documentation.
Of the legal requirements listed above, FHWA identifies the Endangered Species
Act, the Clean Water Act, Section 4(f) of the DOT Act, and the National Historic
Preservation Act as the statutes most likely to apply to all highway projects and most
likely to affect highway project delivery. Unlike NEPA, which is essentially a
procedural requirement, the “big four” statutes prohibit or limit activity, depending
upon the resource impacted.
Appropriate NEPA Documentation
FHWA regulations identify the following three classes of actions that will
dictate the NEPA documentation required for a highway project:15
!Actions with a significant environmental impact - such projects require the
preparation of an Environmental Impact Statement (EIS). When an EIS is
approved, a Record of Decision (ROD) is issued.
!Actions that have no significant individual or cumulative environmental
impacts - such actions are categorically excluded from the requirement to
prepare an EIS; whether and what types of documentation will be required
depends upon the complexity of the project and resources impacted.
!Actions for which environmental impacts are initially uncertain - such
projects require the preparation of an Environmental Assessment (EA) to
determine if an EIS is necessary. If no EIS is required, a Finding of No
Significant Impact (FONSI) is issued.
As illustrated by the classes of actions listed above, to determine the type of
NEPA documentation that is appropriate for any given project, it must first be
determined if the project’s impacts are “significant.” Almost every federal action has
some impact on the environment. CEQ regulations require federal agencies to
determine the significance of those actions by considering the project’s context and
intensity.16
Determining the context of a project involves analyzing impacts to society as a
whole, the affected region, or the locality. The degree of significance must be
considered on a project-by-project basis and will depend upon factors such as the
location and scope of the project. For example, a highway project that impacts one


14 Executive Order 11988: Floodplain Management and Executive Order 11990: Protection
of Wetlands.
15 23 CFR 771.115
16 40 CFR 1508.27

acre of a 2,000-acre wetland may be insignificant, compared to a project that impacts
one acre of a two-acre wetland. The value and function of the impacted wetlands
would also be relevant.
The intensity of an impact refers to its severity. Factors used to assess intensity
will differ from project to project. Factors to consider may include unique
characteristics of the geographical area, the degree to which the action adversely
impacts endangered species or historic sites, or the degree to which the proposed
action affects public health or safety. To adequately determine an impact’s intensity,
more than one agency may need to be involved. For example, the Department of
Agriculture may need to determine the intensity of impacts from a project that would
cut through prime farmland.
Since degrees of impact, with regard to both context and intensity, must be
evaluated to determine project significance, such an evaluation may be highly
subjective.17 While court decisions have been rendered regarding most elements of
NEPA implementation, few federal courts have attempted to specifically define
“significance.” Most often, a court will determine whether the evidence for a given
project involved potentially significant environmental effects and then decide
whether the agency’s decision not to prepare an EIS was reasonable under
circumstances specific to that project.18
Documentation Required When Impacts Are Significant. If it is
determined that the impacts of a proposed project will likely be significant, an EIS
must be prepared. An EIS is a full disclosure document that provides a description
of the proposed project, and the existing environment, as well as analysis of the
anticipated beneficial and adverse environmental effects of all reasonable
alternatives. Preparation is done in two stages, resulting in a draft and final EIS.
As soon as practicable after its decision to prepare an EIS, the agency preparing
the EIS (in the case of highway projects the agency would be FHWA) is required to
publish a notice of intent (NOI) in the Federal Register.19 The NOI acts as the formal
announcement of the project to the public and to interested federal, state and local
agencies. For FHWA projects, this process generally begins in conjunction with the
preliminary design stage of a highway project.
As soon as possible after, or in conjunction with, the determination that an EIS
is needed, the FHWA is required to determine the scope of the project.20 The role of
other agencies and other environmental review and consultation requirements should


17 In determining a project’s significance, the cost of the project is not an element of
consideration.
18 Dinah Bear, “NEPA at 19: A Primer on an ‘Old’ Law with Solutions to New Problems,”
Environmental Law Review, 19 ELR 10060 (Feb. 1989). This article is posted on the CEQ
website under “CEQ Reference.”
19 40 CFR 1508.22
20 40 CFR 1501.7

be established during the scoping process.21 It is during the scoping process that the
agency should determine which statutory requirements or executive orders will apply
(i.e., the applicant will review all laws and executive orders listed in Table 1 to
determine which, if any, will apply to the project). For example, it should be
determined early in the project whether property of historical significance is impacted
or if the project will raise environmental justice issues.
Once the initial scoping is complete, EIS preparation can begin. Significant
elements of an EIS include:
!Project Purpose and Need
!Project Alternatives
!Affected Environment
!Environmental Consequences
!Agency Comments and Coordination
!Public Comments
Each of these elements is discussed below.
Delineation of Project Purpose and Need. CEQ requires one section of
the EIS to be devoted to clarifying the purpose and need for the project. By virtue
of the fact that an EIS is being prepared, a transportation project is anticipated to
have significant environmental, social, or economic impacts. Such a project can be
expected to require the expenditure of a significant amount of funds. The public and
decisionmakers will require a clear, well-supported explanation for why such a
project should be built. When adverse environmental impacts are significant, it is
also important to justify why such impacts are acceptable in light of the
transportation needs being met by the project.
The Purpose and Need section is the foundation upon which subsequent sections
of the EIS are built. FHWA requires the discussion to be clear, specific, and support
the need for the project. A well defined and well justified purpose and need
evaluation will facilitate the development of reasonable project alternatives. For
example, if a project’s purpose involves addressing a traffic capacity problem,
potential means of solving that problem will be considered in the proposed
alternatives. Some of the common needs presented in FHWA EISs include: safety
improvements, increased highway capacity, urban transportation plan consistency,
and system linkage.
The clear delineation of project purpose and need is also necessary to meet the
requirements under Section 4(f), the Executive Orders on wetlands and floodplains,
and the Section 404 permitting requirements.
Development and Analysis of Alternatives. Once the purpose and need
for a project have been clearly delineated, the potential alternatives to meet that


21 CEQ has issued a variety non-regulatory guidance which is used by FHWA in preparing
and processing environmental documents during the scoping process (see the CEQ NEPA
Guidance web page at [http://ceq.eh.doe.gov/nepa/regs/guidance.html])

purpose and need can be evaluated and determined. CEQ regulations refer to the
Alternatives section of the EIS as the “heart” of the document.22 CEQ regulations
require agencies to discuss a range of alternatives that will include all “reasonable
alternatives” under consideration as well as any other alternatives that were
considered but subsequently eliminated from consideration (i.e., a mass transit
alternative may not be reasonable for a given project, but may still need to be
acknowledged). Reasonable alternatives include those that are practical or feasible
from the technical and economic standpoint and using common sense, rather than
simply desirable from the standpoint of the agency or a potentially affected
stakeholder. 23
FHWA regulations require that alternatives considered ensure that the project:
connects logical termini; have independent utility; and not restrict consideration of
future transportation alternatives.24 The Alternatives section should begin with a
concise discussion of how and why the reasonable alternatives were selected for
detailed study and explain why other alternatives were eliminated. FHWA
specifically requires the following range of alternatives to be considered when
determining reasonable alternatives:
!“No-action” alternative: may include activities such as short-term minor
restoration activities (e.g., safety and maintenance improvements) that
maintain continuing operation of the existing roadway.
!Transportation System Management (TSM) alternative(s): activities which
maximize the efficiency of the present system. Possible subject areas to
include in this alternative are options such as ride-sharing, the addition or
designation of high-occupancy vehicle (HOV) lanes on existing roadways,
and/or traffic signal timing optimization.
!Mass Transit alternative(s): reasonable and feasible transit options (e.g., bus
systems, rail) even though they may not be within FHWA funding authority
(when such an alternative is considered, FHWA coordination with the Urban
Mass Transportation Administration is necessary ).
!Build alternatives: construction activities such as the improvement of existing
highway(s) or alternatives in a new location.25
A discussion of the “no-build” alternatives (no-action, TSM, or mass transit
alternative) can serve as a baseline against which “build” alternatives are compared.
It provides an agency with an opportunity to explore and discuss options such as the
designation of HOV lanes, changes in mass transit, or the creation of ride-sharing


22 40 CFR 1502
23 From response to question regarding the “Alternatives Outside the Capability of
Applicant or Jurisdiction of Agency” in Forty Most Asked Questions Concerning CEQ’s
National Environmental Policy Act Regulations, published in the Federal Register at 46 FR

18026, March 16,1981.


24 23 CFR 771.111(f)
25 These choices are specified in FHWA Technical Advisory T6640.8A, October 30, 1987,
entitled “Guidance for Preparing and Processing Environmental and Section 4(f)
Documents,” available online [http://www.fhwa.dot.gov/environment/nepa/ta6640.htm].

programs. Also, in instances where impacts are particularly adverse, the no-build
alternative may prove to be a viable alternative if the need is relatively minor.
With regard to the “build alternatives,” large, complex projects may have the
potential for a large number of reasonable alternatives. Where this is the case, CEQ
suggests that only a representative number of the most reasonable examples, covering
the full range of alternatives, should be presented.26 The determination of the number
of reasonable alternatives in the draft EIS, therefore, depends on the particular project
and the facts and circumstances in each case.
Identification of the Affected Environment. CEQ regulations require that
one section of the EIS be devoted to describing the environment of the area affected27
by each alternative under consideration. FHWA guidance suggests that this section
includes a description of the existing social, economic, and environmental setting of28
the area potentially affected by all alternatives presented in the EIS. Data to include
in this section may include demographics of the general population served by the
proposed project, as well as an identification of socially, economically, and
environmentally sensitive locations or features in the proposed project area. For
example, the EIS should identify the presence of impacted minority or ethnic groups,
parks, hazardous material sites, historic resources, or wetlands.
Identification of Environmental Consequences. One section of the EIS
must identify the specific “environmental consequences” (i.e., impacts or effects) of
each alternative. It is within this section that methods of compliance with applicable29
legal requirements may be discussed and demonstrated. An explanation of
environmental consequences involves a discussion of the probable beneficial and
adverse social, economic, and environmental effects of each alternative. Also
included would be a description of the measures proposed to mitigate adverse
impacts.
CEQ regulations specify minimum criteria for evaluating environmental
consequences.30 For example, this section must include, where applicable, a
discussion of both the direct and indirect effects of each alternative and the
significance of those effects.
FHWA also has identified 25 environmental consequences potentially applicable
to highway projects (see Table 2). For example, one potential environmental
consequence regards “Historic and Archeologic Preservation.” If a project alternative
results in such an environmental consequence, the draft EIS may require a discussion


26 From responses to questions regarding the “range of alternatives” in Forty Most Asked
Questions Concerning CEQ’s NEPA Regulations.
27 40 CFR 1502.15
28 See FHWA Technical Advisory T6640.8A, October 30, 1987, Section V.F.
29 The environmental consequences potentially relevant to a given transportation project
would be regulated under the statutes and executive orders listed Table 1.
30 40 CFR 1502.16

demonstrating that such resources have been identified and evaluated in accordance
with all legal requirements under Section 4(f) or Section 106 of NHPA.
FHWA recommends that the environmental consequences section be devoted
largely to a scientific analysis of the direct and indirect environmental effects of the
proposed action relative to each alternative. The FHWA may need input from other
federal, state, or local agencies with expertise on the environmental consequences
under review. For example, FHWA may need assistance in determining
environmental consequences to threatened or endangered species, coastal zones,
floodplains, or air quality.
Table 2. Potential Types of Environmental Consequences to be
Considered for Transportation Projects
Land Use Impacts Floodplain Impacts
Farmland Impacts Wild & Scenic Rivers
Social Impacts Coastal Bariers
Relocation Impacts Coastal Zone Impacts
Economic Impacts Threatened/Endangered Species
Joint Development Historic & Archeological Preservation
Considerations Relating to Pedestrians Hazardous Waste Sites
& Bicyclists Visual Impacts
Air Quality Impacts Energy
Noise Impacts Construction Impacts
Water Quality Impacts Relationship of Local Short-term Uses vs.
PermitsLong-term Productivity
Wetland Impacts Irreversible & Irretrievable Commitment
Water Body Modification & Wildlifeof Resources
Impacts
Source: Table prepared by the Congressional Research Service (CRS) based on data from the FHWA
Technical Advisory T6640.8A
Agency Comments and Coordination. NEPA projects involve the
participation of a “lead agency” and “cooperating agencies.” The lead agency is
defined as the federal agency that has taken responsibility for preparing the NEPA
documentation.31 For federally funded highway projects, the lead agency will usually
be FHWA. State or local agencies, such as state DOTs, will likely act as joint lead
agencies. The project applicant will initially develop substantive portions of the
environmental document, while FHWA will be responsible for its scope and
content.32 FHWA requires that the draft and final EIS demonstrate that appropriate
comments and coordination were solicited from relevant federal, state and local
cooperating agencies.
Cooperating agencies required to provide input on an EIS are those that are
obligated to provide comments within their agency’s jurisdiction, expertise, or
authority. This means that the federal agency with jurisdiction over or expertise


31 40 CFR 1508.16
32 23 CFR 771.109(c)

regarding any identified environmental consequence is required to provide FHWA
with the appropriate input. For example, if historical and archeological preservation
consequences are identified, the Advisory Council on Historic Preservation will
likely be included as one of the cooperating agencies during the NEPA Process. If
farmland impacts are identified, the draft EIS should summarize the results of
comments and coordination with the U.S. Department of Agriculture (USDA) and,
as appropriate, state and local agriculture agencies.
If a cooperating agency, or any other federal, state or local agency participating
in the NEPA Process, comments on a NEPA document, FHWA is required to assess
and consider those comments and respond in one of the following ways:33
!Modify proposed alternatives.
!Develop and evaluate alternatives not previously considered.
!Supplement, improve, or modify its analyses.
!Make factual corrections to the EIS.
!Explain why the comments do not warrant further agency response from
FHWA, citing the sources, authorities, or reasons which support the agency’s
position and, if appropriate, indicate those circumstances which would trigger
agency reappraisal or further response.
Under CEQ regulations, lead agencies are required to invite comments,
cooperating agencies have a duty to respond to environmental documents, and lead
agencies are required to respond to those comments. However, as illustrated in the
choices listed above, the lead agency is not precluded from moving forward with a
project if it explains why a cooperating agency’s comments do not warrant further
response.
Public Involvement. One of the primary goals of NEPA is to allow the
public a meaningful opportunity to learn about and comment on the proposed actions
of the federal government. It is the intent of NEPA that agencies encourage and
facilitate public involvement in decisions that affect the quality of the human
environment and make a diligent effort to involve the public in preparing and
implementing their NEPA procedures. To meet these goals, agencies are required
to provide public notice of NEPA-related hearings, public meetings, and the
availability of environmental documents so as to inform public stakeholders that may
be interested in or affected by a proposed project. Any documentation related to the
public’s participation in the NEPA process (i.e., comments or hearings transcripts)
must be included in the final EIS.
Stakeholders who may comment on surface transportation projects will vary
according to the impacts of each project. They may include individuals or groups
expected to benefit from or be adversely impacted by the project, or special interest
groups with concerns about the project’s impacts on certain affected environments.
For example, consider a highway project that involves upgrading existing roadways,
the construction of which would impact adjacent homes or businesses. Such a
project may elicit comments from the local business community (e.g. individual


33 40 CFR 1503.4

businesses, the Chamber of Commerce, or local development organizations) or area
home owners. A project with impacts to sensitive environmental resources, such as
wetlands or endangered species, may generate comments from local or national
environmental organizations.
If a stakeholder has concerns about a project’s impacts, their comments may be
directed at virtually any element of the NEPA process or related documentation.
While not an exhaustive list, following are examples of topics on which a stakeholder
may comment:
!Purpose and need determination – stakeholders may assert that a project’s
purpose and need discussion was not sufficiently broad, meaning the scope of
the purpose and need was so narrow that only a limited number of alternatives
could be chosen.
!Alternatives selection – stakeholders may assert that all “reasonable”
alternatives were not considered. They may assert that additional alternatives
exist that were not considered. This may be the case particularly for
controversial projects that are not welcomed by impacted communities or
special interest groups.
!Alternatives analyses – stakeholders may assert that proposed alternatives
were not analyzed sufficiently to determine all potential environmental
consequences.
!Issues with documentation – a stakeholder may assert that all regulatory
requirements were not fulfilled. For example, they may assert that required
findings were not documented (e.g., proof of compliance with all applicable
laws was not documented) or that required evaluations or reviews were not
sufficiently illustrated (e.g., the presence of endangered species or impacts to
historic sites was not properly evaluated, or consideration of social and
economic impacts was not demonstrated).
!Issues regarding project significance – stakeholders may disagree with the lead
agency’s determination of the project’s significance. For example, they may
assert that a project for which an EA was prepared should have required an
EIS, or they may feel that a project approved as a categorical exclusion was
questionable and required the more in-depth review of an EA.
Any one of the topics listed above could be the subject of legal action, and has
been in the past. For example, FHWA personnel have indicated that a recent court
decision is now commonly used as the benchmark in developing the appropriate
purpose and need statement and resulting scope of project alternatives during the
NEPA process.34 Plaintiffs in this case were affected landowners who brought suit
against the U.S. Army Corp of Engineers in response to their issuance of a permit to
build a dam. In his decision, the judge stated, “One obvious way for an agency to
slip past the strictures of NEPA is to contrive a purpose so slender as to define
competing ‘reasonable alternatives’ out of consideration (and even out of existence)
... If the agency constricts the definition of the project’s purpose and thereby excludes
what truly are reasonable alternatives, the EIS cannot fulfill its role.”


34 See Simmons v. U.S. Army Corps of Engineers, 120 F.3d 664 (1997).

To a large degree, the manner in which FHWA implements NEPA is dictated
by such judicial decisions. To avoid conflict after a project has reached an advanced
stage of development, FHWA recommends that continuous contact with non-agency
stakeholders be maintained throughout the decisionmaking process– from the earliest
project planning stages, as one or more transportation problems are identified,
through defining purpose and need, through the development of a range of potential
alternatives, and up to the decision to select a particular alternative.
Record of Decision. Not less than 30 days after publication of the final EIS
notice in the Federal Register, a Record of Decision (ROD) is signed. The ROD will
present the basis for the Agency’s final decision, summarize any mitigation measures
that will be incorporated in the project, and document any approval of resources
regulated under Section 4(f). Final design activities, property acquisition, purchase
of construction materials, or project construction cannot begin until the ROD has
been signed.
Documentation Required When Impacts are Not Significant.
Transportation projects that do not individually or cumulatively have a significant
social, economic, or environmental effect, and which FHWA has determined from
past experience have no significant impact, are excluded from the requirement to
prepare an EIS or Environmental Assessment (discussed below). Such actions are
processed as categorical exclusions (CEs) and make up almost 91% of the projects
processed by FHWA. Even if a project’s impacts are not significant, CEQ and
FHWA regulations may require a certain degree of documentation to prove that the
highway project is undertaken in compliance with all applicable environmental
requirements (see Table 1).35
Even though categorically excluded projects have insignificant environmental
impacts, depending upon the action, some documentation may be required to prove
that the CE determination is appropriate and that any required environmental review
or analysis has occurred. As discussed previously, statutory requirements to conduct
certain environmental reviews may still be required, regardless of whether impacts
are deemed significant under NEPA. For example, any impacts to a 4(f) resource
must be evaluated. Also, documentation regarding the assessment of impacts to
endangered species habit may be required.
FHWA regulations specify two groups of activities that experience has shown
would meet the definition of a CE. Whether and what type of documentation will be
required, before the project could be approved by FHWA, would depend on within36
which of the two groups the action falls.
The first group includes projects that call for no or limited construction.
Examples include the construction of bicycle and pedestrian lanes, paths, and
facilities, landscaping, the acquisition of scenic easements, emergency repairs, and
the installation of fencing, signs, pavement markings, small passenger shelters, or
traffic signals. Normally such projects do not require any further NEPA approvals


35 23 CFR 771.133
36 Each group of potential CEs is listed under 23 CFR 771.117(c) and (d).

by FHWA. However, requirements of other laws may still apply. For example,
construction of a bicycle path or installation of traffic signals in a historic district may
require compliance with Section 106 or Section 4(f). While requirements under
NEPA indicate that such a project has no significant impact, documentation of
compliance with additional statutory requirements may be required to approve the
project’s CE status.
The second group of projects consists of actions with a higher potential for
impacts than the first group, but which still meet the criteria for a CE because
environmental impacts are minor. An example of such a project is the modernization
of a highway through resurfacing, reconstruction, adding shoulders, or adding
auxiliary lanes. Whether or not such actions will have a significant impact on the
environment depends largely on where they are located. Where adverse
environmental impacts are likely, FHWA recommends that the level of analysis be
sufficient to define the extent of impacts, identify appropriate mitigation measures,
and address known and foreseeable public and agency concerns. At a minimum,
documentation must include a description of the proposed action and, as appropriate,
its immediate surrounding area, a discussion of any specific areas of environmental
concern (e.g., historic sites or wetlands), and a list of other federal actions required,
if any, for the proposal.37
Documentation Required When the Significance of Impacts is
Uncertain. An environmental assessment (EA) is prepared when it is uncertain
whether a project’s impact will be significant. The EA should briefly provide
evidence and analysis for determining whether to prepare an EIS (i.e., whether the
project’s impacts are significant).38 If at any time during preparation of the EA, it is
determined that a project’s impacts are significant, EIS preparation should begin.
There is no standard format for EAs required by either CEQ or FHWA
regulations. FHWA suggests that the process for developing an EA should be similar39
to developing an EIS. For example, the applicant should consult interested agencies
to scope the project to determine the potential for social, economic or environmental
impacts; briefly discuss the project’s purpose and need; identify project alternatives
and measures to mitigate adverse impacts; and identify any other environmental
review requirements applicable to the project (i.e., section 4(f) or 404 permitting
requirements).
The EA and other relevant documents (e.g., public comments or hearing
transcripts) must be submitted to the FHWA with a request for a Finding of No
Significant Impact (FONSI). FHWA requires that the basis for the FONSI request
be clearly and adequately documented. Like an EIS, the EA or FONSI is required to
clearly document compliance with NEPA and all other applicable environmental
laws, executive orders, and related requirements. An approved FONSI serves the
same purpose that a ROD serves with an EIS. Similarly, final design activities,


37 This guidance is provided in FHWA Technical Advisory T6640.8A
38 40 CFR 1508.9
39 See FHWA Technical Advisory T6640.8A, Section II, “Environmental Assessments.”

property acquisition, purchase of construction materials, or project construction
cannot begin until the FONSI has been approved.
FHWA estimates that projects requiring an EA, and no subsequent EIS,
accounted for almost 7% of highway projects approved in 2001. Coupled with
categorically excluded projects discussed above, this means that close to 97% of all
projects approved by FHWA are determined to have no significant impact on the
environment. Figures 1 and 2 illustrate the percentage of FHWA projects by the
threes classes of action discussed above and by funding amounts for 1998 through
2001. Note that while projects requiring an EIS are often the most complex and
costly, on average, such projects still account for less than 10 percent of total FHWA
project funding.
Figure 1. FHWA Projects by Class of Action
Figure 2. FHWA Project Funding by Class of
Action
Source: FHWA, available at [http://www.fhwa.dot.gov/environment/strmlng/projectgraphs.htm].



Determining NEPA’s Role in Transportation Project Delays
The process of both compliance with and documenting compliance with all
environmental statutes, regulations, executive orders, and court decisions potentially
applicable to a highway project is complicated. As has been discussed, even those
projects with no or minor environmental impacts must demonstrate that potential
impacts to certain types of resources (i.e., public parkland, historic sites, land with
threatened or endangered species, or property in minority neighborhoods) have been
considered and that compliance with applicable requirements documented.
The perception that NEPA results in extensive delays and additional costs to the
successful delivery of transportation projects can be magnified when compliance with
multiple environmental laws and regulations is required (as would likely be the case
with large, complex highway projects). FHWA has asserted that many delayed
projects or failed processes can be traced back to a disintegrated and disconnected
approach to meeting NEPA and other requirements. FHWA asserts that their
experience in administering NEPA has shown that many practitioners do not fully
understand or practice the approach to using the NEPA process as an umbrella for
integrating all required studies, reviews, or consultations.40
The sometimes extensive reviews required by agencies such as the Army Corps
of Engineers, the Fish and Wildlife Service, the Coast Guard, or EPA, as well as
various state regulatory and review agencies, add further to the perception that
extensive delays are related to the “NEPA process.” Such delays may actually be a
result of an agency’s need to complete a permitting processes or other analyses under
separate statutory authority (e.g., the Clean Water Act or Endangered Species Act),
over which FHWA has no authority.
A project with significant impacts would likely be a large, high-profile, complex
project costing millions of dollars. Delays of such projects are well-known among
transportation professionals and have garnered significant public attention in the past.
For example, in the Washington, D.C. area, replacement of the Woodrow Wilson
Memorial Bridge is a well-known FHWA project. Challenges to the NEPA
documentation for that project resulted in delays to the project. However, much of
the delay was only indirectly related to the NEPA process, in that the project has
highly visible and generated significant public interest. Often, similar high-profile
projects have been delayed by public challenges to elements of the NEPA
documentation. However, until recently, there was only anecdotal information
directly linking the “NEPA process” to widespread highway project delays.
Studies Examining NEPA’s Role in Project Delays. Federal and state
governments do not routinely maintain information on the time it takes to complete
highway projects. Therefore, gathering accurate data specific to the time it takes to
prepare NEPA documentation is difficult. For example, document preparation under
NEPA is generally done concurrently with preliminary project design. If a project
undergoes specification changes, those changes may necessitate changes in NEPA
documentation. Consequently, the time to complete the NEPA process may be


40 Notice of Proposed Rulemaking, 65 FR 33965, page 33976.

extended. However, determining if such delays can be directly attributed to the
NEPA process itself may be difficult. Several studies, conducted by both the General
Accounting Office (GAO) and FHWA have attempted to define that connection. The
findings of these studies are discussed below.
2002 GAO Report. In the absence of data to determine project development
time frames, GAO compiled data based on the professional judgement of FHWA
staff, staff of state departments of transportation, and transportation associations.41
FHWA estimated that it typically takes from 9 to 19 years to plan, gain approval for
and construct a new major, federally-funded highway project that has significant
environmental impacts (i.e., requires an EIS). Such projects were completed in four
phases as outlined in Table 3.
Table 3. Estimated Time to Complete Federally Funded Highway Projects
PhaseTime to Complete (years)
Planning4-5
Preliminary design and environmental review1-5
Final design and right-of-way acquisition2-3
Construction2-6
Total9-19
Source: FHWA, as quoted by GAO.
GAO noted that the wide range in time for each phase is attributed to the
inherent variations in project size, complexity, and public interest in the project. In
the study, FHWA noted that the “preliminary design and environmental review”
phase often overlapped with the “final design and right-of-way acquisition” phase.
Federal and state officials reported that larger, more controversial projects were likely
to take longer because they generally required compliance with more federal and state
requirements and because of the public interest they may generate.
Federal and state transportation officials and transportation engineering
organizations contacted by GAO identified the timely resolution of environmental
issues as providing the greatest opportunity for reducing the time it takes to complete
highway projects. Those officials generally stated that environmental reviews
resulted in better project decisions; but reaching those decisions was difficult and
time consuming. Factors that could make the process more difficult included:
incomplete permit applications, limited resources at environmental agencies, and
public opposition to projects.


41General Accounting Office, Highway Infrastructure: Preliminary Information on the
Timely Completion of Highway Construction Projects, GAO-02-1067T, September 19,

2002.



FHWA NEPA Baseline. Among the data used in the 2002 GAO report,
referenced above, was information from an FHWA study completed in 2001.42 In
that study, FHWA undertook an analysis of the direct effect that compliance with the
requirements of NEPA has on the ultimate schedule and cost of delivering a
completed transportation project. The report is to be used to establish a baseline
against which progress on its streamlining initiatives will be gauged. The study was
also intended to provide a better understanding of the impacts of the NEPA process
on the total time involved in completing a Federal-aid highway or bridge project, as
well as individual factors influencing the time required to complete the NEPA
process in order to develop performance measures for future improvement.
In the baseline study, FHWA acknowledged the perception that NEPA is the
cause of delays and additional cost to the delivery of transportation projects. FHWA
asserted that what was missing from the discussion was an analysis of the direct
effect that compliance with the requirements of NEPA has on the ultimate schedule
and cost of delivering a completed transportation project. The baseline study
attempted to determine or define that connection. Following are significant
conclusions drawn by the FHWA study:
!For projects requiring an EIS, the mean time required for the entire project
development process was approximately 13.1 years.
!For projects requiring an EIS, the NEPA process generally comprises
approximately 27% to 28% of that total project development period (from the
time that either preliminary engineering or the NEPA process begins,
whichever is first, to the end of construction).
!The time to prepare an EIS has increased from a mean of 2.2 years in the

1970s to a mean of 5.0 years in the 1990s.


!The time to prepare an EIS increased by almost two years when a Section 404
permit or Section 4(f) approval was also required (e.g. the average time to
complete an EIS was 4. 3 years when a Section 404 permit was involved, but
only about 2. 4 years when no Section 404 permit was involved); the increase
when a Section 106 approval was required was negligible.
!The length of time to prepare an EIS varied between regions, with the greatest
time required in the Northeast (with a median value of 4.5 years) and the least43
time required in the Northwest (with a median value of 1 year).
During Congressional oversight hearings on streamlining, transportation
stakeholders have noted the increase in time to complete an EIS from the 1970s to44
the 1990s. In its baseline study, FHWA does not comment on the cause of this


42 See FHWA’s Evaluating the Performance of Environmental Streamlining: Development
of a NEPA Baseline for Measuring Continuous Performance, May 8, 2001, available at
[ h t t p : / / www.f h wa.dot .gov/ e nvi r onment / s t r ml ng/ b asel i n e] .
43 The value of quoting “mean” versus “median” number of years, in looking at a given
statistic, was discussed in the survey. It was determined that, since NEPA data were not
normally distributed, the mean, or average, value was not always a good indicator of central
tendency. Therefore, in some instances, it was determined that the median, or mid-point
value, was the most relevant value.
44 See testimony of John C. Horsley, Executive Director of the American Association of
State Highway and Transportation Officials; Brian Holmes, Executive Director, Maryland
Highway Contractors Association, on behalf of the American Road & Transportation
Builders Association; and Hal Kassoff, Vice President, Parsons Brinckerhoff, on behalf of
(continued...)

increase. However, there are a variety of factors that contribute to lengthened
reviews. For example, the process for completing an EIS in the 70s differs
substantially from the process undertaken in the 90s. Until November 1978, there
were no CEQ regulations outlining EIS requirements. While an EIS may have been
completed relatively quickly during the 70s, compared to the 90s, it may not have
withstood judicial review. FHWA did not promulgate its own regulations until 1987.
Such regulations may have served to make the process take longer, but may have
resulted in fewer overall project delays, in situations where adherence to the
regulations resulted in a more legally sound EIS. Also, the complexity of projects in
the 1970s are not comparable to those of the 1990s and public is more involved in
the highway construction process in the 1990s than was the case in the 1970s.
The difference in time to complete projects from region to region may be
attributed to differences in the types of projects likely to occur in those regions. For
example, projects in the Northeast that simply expand or upgrade existing highway
systems, but occur in the heavily-developed regions, may involve a wide range of
significant impacts. While projects in the less-developed Northwest may generate
fewer overall impacts and be easier to implement.
FHWA Study of EIS Delays. In September 2000, FHWA issued a study that45
explored causes of delay of certain projects requiring an EIS. This study was done
in response to a question submitted by the House Committee on Transportation and
Infrastructure in March 2000 regarding causes of delay for highway projects that had
not had a ROD approved after five years. FHWA identified 89 projects that fit the
specified criteria.
Survey respondents were asked to provide a brief assessment of the reasons that
each project had taken more than five years to complete the NEPA process. In the
study, over 60% of project delays could be attributed to lack of funding, low priority,
local controversy, or project complexity. The results of this report were often quoted
by interested stakeholders as evidence that neither NEPA, nor any environmental
issues related to NEPA compliance, was a significant cause of transportation delays.
At the request of Representative Don Young, GAO reviewed the FHWA study’s46
methodology to determine the usefulness of its results. In the report, released in
January 2003, GAO determined that some elements of the study’s methodology
called into question the usefulness of the final results. For example, if respondents
provided more than one cause of project delays, only one response was included,
typically the answer written first. It could not be definitively determined if the one


44(...continued)
the American Council of Engineering Companies, before the Subcommittee on Highways
and Transit Committee on Transportation and Infrastructure, United States House of
Representatives, October 8, 2002.
45 FHWA, Reasons for EIS Project Delays, available at
[ h t t p : / / www.f h wa.dot .gov/ e nvi r onment / s t r ml ng/ e i s del a y.ht m# i mage] .
46 General Accounting Office, Federal Highway Environmental Analysis, GAO-03-338R,
January 16, 2003.

answer chosen was the most serious cause of delay, or if multiple causes were
similarly relevant.
In the 2003 report, GAO concluded that, by relying on often general narrative
responses, without directing its division offices to indicate the relative importance
of responses, FHWA limited its ability to provide useful insights. Furthermore, by
not describing its methodology, FHWA limited the ability of the Congress and the
public to evaluate the strengths and weaknesses of the study in order to understand
its reliability. In response to the GAO report, FHWA has updated its study results
to explain the survey methodology.

2003 GAO Reports on Stakeholder Views of the NEPA Process.


Perceptions regarding the time it takes to conduct required environmental reviews for
highway projects vary among stakeholders. This is the finding of a May 2003 GAO
report that looked at the views held by environmental stakeholders and transportation
improvement stakeholders.47 “Environmental stakeholders” included resource
agencies, state historic preservation agencies, and environmental advocacy
organizations. “Transportation improvement stakeholders” included state
departments of transportation, FHWA division offices, and transportation advocacy
organizations.
Stakeholders of highway construction projects contacted by GAO identified 43
aspects that they said added undue time to complete an environmental review of
federally funded highway projects. “Undue time” was considered more time than the
stakeholder viewed as necessary to complete the review. Of the 43 total aspects
identified, five were identified by one or both groups of stakeholders as occurring
most frequently (see Table 4). Each group of stakeholders disagreed on the degree
to which each of those five aspects impacted the review process.
Table 4. Environmental and Transportation Improvement Stakeholders’
Most-Frequently Cited Aspects Adding “Undue Time” to Environmental
Reviews of Highway Projects.
Environmentala Transportation
Aspect IdentifiedStakeholdersStakeholders
State DOTs do not consider environmental and70%13%
historic preservation impacts early enough in
the highway planning process.
State DOTs do not include important6419
stakeholders early enough in the process.
State DOTs lack sufficient staff to perform5069


responsibilities in a timely manner.
47 General Accounting Office, Highway Infrastructure: Stakeholders’ Views on Time to
Conduct Environmental Reviews of Highway Projects, GAO-03-534, May 23, 2003.

Requirements under “Section 4(f)” are3056
burdensome.
Obtaining wetlands permits under Section 404056
of the Clean Water Act is time consuming.
a Values listed represent the percentage stakeholders in each category that chose this aspect as one
that added undue time to the environmental review process.
Source: Table prepared by the Congressional Research Service (CRS) based on data from the GAO
analysis of stakeholder response presented in GAO-03-534, pg. 6.
Findings in the May 2003 GAO report were consistent with findings in an April
2003 GAO report on stakeholder perceptions of the most promising approaches to
to reduce completion time for highway projects (as opposed to perceptions of causes
of delays).48 The April 2003 GAO report looked at all aspects of a highway project
from planning through construction. In this report, survey respondents were from
organizations representing a wide range of federal, state, tribal, and advocacy
interests. Following are approaches identified by a majority of respondents that were
deemed most promising with regard to improving the environmental review process:
!Establish early partnerships and coordination among stakeholders so that
technical, environmental, policy, and other issues can be resolved in a timely
and predictable manner (identified by 90% of all respondents).
!Revise Section 4(f) – use Section 106 procedures for consideration of historic
properties and other historic resources (70%).
!Use programmatic agreements as a means of delegating review or permitting
authority to states for routine projects or commonly occurring resource effects
(68%).
!Establish time frames for environmental reviews (60%).
!Use interagency funding agreements to provide staff at resources agencies
(59%).
!Prepare a preliminary environmental assessment report that will provide
information on any environmental conditions and constraints before
determining project costs or schedule (53%).
!Unify NEPA and Section 404 reviews so that Section 404 reviews are
addressed concurrently with other environmental issues (58%).
In the April report, GAO recommended that FHWA consider the benefits of the
most promising approaches and act to foster the adoption of the most cost effective
and feasible approaches. FHWA generally agreed with this recommendation and
stated that most, if not all, of the most promising approaches coincide with its current
streamlining activities.


48 General Accounting Office, Highway Infrastructure: Perceptions of Stakeholders on
Approaches to Reduce Highway Project Completion Time, GAO-03-398, April 2003.

The Transportation Equity Act for the 21st Century
In 1998, Congress passed the Transportation Equity Act for the 21st Century
(TEA-21, P.L. 105-178) that reauthorized the federal surface transportation programs
for highways, highway safety, and transit for the fiscal years 1998-2003. During the
reauthorization process, states reported to Congress that the numerous federal
environmental approvals and permits needed to build a highway were inefficient and
overly time-consuming. To address these concerns, Congress included in TEA-21
Section 1309, “Environmental Streamlining,” which was intended to better
coordinate federal agency involvement in the NEPA process. Although not
specifically defined in TEA-21, FHWA defines environmental streamlining as the
timely delivery of federally-funded transportation projects, while protecting and
enhancing the environment. A summary of the streamlining provisions of TEA-21
and the Administration efforts to implement them are discussed below.
“Streamlining” Provisions of TEA-21. The streamlining provisions in
Section 1309 of TEA-21 were intended to better coordinate federal agency
involvement in the NEPA process. Following are key elements of Section 1309:
!Directs the Secretary of Transportation to establish a “coordinated
environmental review process” that, among other provisions, establishes time
frames for completion of the environmental review process;
!Directs the Secretary to resolve interagency disputes when established time
limits are not met;
!Allows state DOTs to direct relevant state agencies to participate in the
coordinated environmental review process; and
!Provides state DOTs with the ability to request funds to reimburse agencies
for expenses associated with expediting environmental reviews.
Coordinated Environmental Review Process. Subsection 1309(a) and
(b) of TEA-21 outlined provisions regarding the development and implementation
of a “coordinated environmental review process.” The Secretary of DOT was
required to develop this process for any project requiring an EIS or EA under NEPA.
The Secretary may, however, choose not to apply this review process to EAs or other
environmental documentation (i.e., reviews, analysis, or permits) required by law.
The coordinated review process may be delineated in a memorandum of
understanding. TEA-21 specified elements to be included in the coordinated review
process. At a minimum it was required to provide:
!The early identification of federal or state agencies with jurisdiction over
environmental issues related to the project or that may be required by law to
participate in the environmental review process;
!The establishment of time frames for completion of any agency comments or
other environmental requirements (i.e., reviews, analyses, opinion, permits,
licenses or approvals), to be determined jointly by DOT and the agencies
identified for participation; and
!A requirement that time frames for completion of requirements be undertaken
by all agencies concurrently, unless the agency can show that the concurrent
review would alter operation of federal law, would result in a significant



adverse impact to the environment, or would not be possible without
information developed as part of the environmental review process.
Established time frames were required to be consistent with current Council of
Environmental Quality (CEQ) regulations and any other environmental regulations.
DOT was directed to set time limits for the proposed project as long as the limits are
consistent with the purposes of NEPA.49
Dispute Resolution Procedures. Section 1309(c) allows the Secretary to
close the record on an activity, after notice and consultation with the affected
agency, if the agency has not completed it by an established deadline. If an
unresolved matter involves an activity required by law, the Secretary and the agency
are directed to resolve the matter within 30 days. However, this section does not give
the Secretary additional authority over agencies outside DOT. Consequently, the
requirement for an agency to meet the 30-day time period would not supersede
statutory responsibilities under other laws (e.g., the Endangered Species Act or Clean
Water Act).
State Agency Participation. Under Section 1309(d), a state may require that
all state agencies, with jurisdiction over environmental issues potentially applicable
to a project, be subject to the coordinated environmental review process unless the
Secretary of DOT determines that a state’s participation would not be in the public
interest. For a state to require state agencies to participate in the review process, all
affected agencies of the state would be subject to the review process.
Financial Assistance and Judicial Review. Section 1309(e) provides
states with the authority to request funds to reimburse affected agencies for expenses
associated with meeting time limits for environmental review, if those time limits are
less than usual. Section 1309(f) specifies that nothing in Section 1309 will affect the
reviewability of any final federal agency action in a U.S. district court or state court,
affect the applicability of NEPA or any other environmental statute, or affect the
responsibility of any federal officer to comply with such statutes.
Of the provisions discussed above, TEA-21's streamlining requirements did not
permit the Secretary to override the authority of another agency to conduct
environmental reviews. For example, the U.S. Fish and Wildlife Service would not
be required to complete biological assessment of an impacted endangered species
within a time frame that would not allow it to meet its own statutory obligations
under the Endangered Species Act.
Administrative Actions to Implement TEA-21. DOT has undertaken a
variety of actions to meet the goals of TEA-21's streamlining requirements.
However, no final regulations have been implemented. In May 2000, under the
Clinton Administration, FHWA submitted a proposed rule on “NEPA and Related


49 Time limits are to be consistent with requirements stipulated under 40 CFR 1501.8 and
1506.10

Procedures for Transportation Decisionmaking.”50 Some commenters indicated that
the proposed rule failed to streamline the review process. Elements of the rule
presented an increased burden of paperwork and procedural requirements, they
argued, and increased the potential for litigation. There was also a concern that the
proposed rule lacked specific provisions addressing the establishment of timeframes,
comment deadlines, dispute resolution, and “closing the record” on decisionmaking
at an appropriate stage. Due to these concerns, the proposed rule was withdrawn by
FHWA under the Bush Administration in September 2002.51
Since withdrawal of the proposed rule came within a year of the legislative
reauthorization of federal surface transportation programs, the agency stated that it
would wait for the outcome of the legislative process to see what further regulatory
changes were needed. In lieu of final regulations, DOT has implemented a variety
of administrative actions in response to TEA-21's streamlining requirements.
Selected actions are described below.
Executive Order Implementation. In September 2002, President Bush
signed Executive Order 13274, “Environmental Stewardship and Transportation52
Infrastructure Project Review.” The Order established a policy that directed federal
agencies to “take appropriate actions, to the extent consistent with applicable law and
available resources, to promote environmental stewardship in the Nation”s
transportation system and expedite environmental reviews of high-priority
transportation infrastructure projects.” To meet this policy, agencies were required
to formulate and implement administrative, policy, and procedural mechanisms to
enable each agency required to participate in the environmental reviews process to
ensure that completion of such reviews occur in a “timely and environmentally
responsible manner.”
Among the criteria required for a project to be designated a “high-priority
project” are whether it is of national or regional significance and whether it may
experience delays from lack of federal interagency coordination. To date, 13 FHWA
projects (10 highway and 3 transit projects) have been chosen for priority review.
As required by the order, an “Interagency Transportation Infrastructure
Streamlining Task Force” was created that is chaired by the Secretary of
Transportation. Task Force members are from federal agencies likely involved in
environmental project reviews. Members include the Secretaries of Agriculture,
Commerce, the Interior, and Defense, the Administrator of EPA, Chairman of the
Advisory Council on Historic Preservation, and Chairman of the CEQ, or their
designee. The Task Force monitors work on expedited projects, reviews the list of
suggested projects, and identifies and promotes policies that aid in streamlining. The
Task Force reports to the President through the Chairman of the CEQ.


5065 Federal Register 33960.
5167 Federal Register 59225.
52 This Executive Order is available at [http://www.fhwa.dot.gov/stewardshipeo/index.htm].

Reports to Congress. Conference report language (H.Rept. 108-10) for the
Consolidated Appropriations Resolution for 2003 (P.L. 108-7) directed FHWA to
provide the House and Senate Appropriations Committees with a report, by April 15,
2003, summarizing FHWA’s streamlining efforts. In April 2003, FHWA submitted
its Report to Congress, providing an update on the status of the accomplishments in
the following areas:53
!Solidifying interagency partnerships
!Re-engineering the environmental review process
!Issuing guidance to enhance process predictability
!Evaluating the performance of environmental streamlining
!Institutionalizing dispute resolution
!Supporting state environmental streamlining efforts
!Sharing information on best practices
FHWA issued a similar Report to Congress in 2002 for environmental54
streamlining activities during 2001. The 2002 report detailed state streamlining
activities and interagency cooperative efforts to facilitate TEA-21's streamlining
requirements.
Dispute Resolution Procedures. FHWA developed the National Dispute
Resolution System, one element of which was the development of guidance to be
used to manage conflict and resolve disputes between state and federal agencies
during the transportation project development and environmental review process.55
Workshops in the application and use of alternative dispute resolution procedures are
currently being scheduled and will use the guidance as the principal reference
document.
Training and Guidance Materials. FHWA has sponsored training,
seminars, and workgroups, and issued a variety of guidance documents aimed at
assisting state DOTs or other federal agencies in implementing the NEPA process
more efficiently. FHWA sponsored workshops with the U.S. Army Corps of
Engineers, EPA, FWS, and NOAA Fisheries. Workshops identified innovative
streamlining practices as well as issues that cause interagency conflict.
In January 2003, FHWA issued interim guidance to help state DOTs analyze
indirect and cumulative impacts and streamline the NEPA process.56 In February

2003, FHWA guidance documents to assist state DOTs in using interagency funding


53 The report is available at [http://www.fhwa.dot.gov/environment/strmlng/final02rpt.htm].
54 This report is available at [http://www.fhwa.dot.gov/environment/strmlng/ssprtcr.htm].
55 “Collaborative Problem Solving: Better and Streamlined Outcomes for All,” February

2003, is available at [http://www.fhwa.dot.gov/environment/strmlng/cmgtnepa.htm].


56 The guidance, “Interim Guidance: Questions and Answers Regarding Indirect and
Cumulative Impact Considerations in the NEPA Process,” January 2003 is available at
[http://www.fhwa.dot.gov/environment/guidebook/qaimpact.htm] and .

agreements to hire additional staff at state and federal resource agencies to speed up
the environmental review process.57
Support of State Streamlining Initiatives. In 2002, the American
Association of State Highway and Transportation Officials (AASHTO) launched the
“Center for Environmental Excellence” with technical and financial assistance from
by FHWA. The Center is intended to assist its members in promoting “innovative
streamlining” of the project delivery process. FHWA is also supporting individual
states in implementing their own streamlining initiatives by providing program
funding and technical support.
Challenges to Streamlining
Late in the 107th Congress, hearings on the streamlining issue were held by the
Senate Environment and Public Works Committee and the House Subcommittee on
Highways and Transit of the Committee on Transportation and Infrastructure. In
conjunction with those hearings, two bills were introduced to address the
streamlining issue, but neither was enacted. Representative Don Young introduced
the Expediting Project Delivery to Improve Transportation and the Environment Act
(H.R. 5455) on September 25, 2002. Senator Baucus introduced the Maximum
Economic Growth for America Through Environmental Streamlining Act (S. 3031)
on October 2, 2002. Both the hearings and proposed bills highlighted a variety of
streamlining issues that some Members of Congress felt needed further attention.
Included among those issues was the need to:
!Better coordinate the NEPA process on a nationwide basis (as opposed to
achieving varying levels of success from state-to-state);
!Establish DOT as the definitive decision maker when determining a project’s
purpose and need and project alternatives;
!Establish a statute of limitations on judicial review of final agency actions;
and
!Delegate more power to the states.
House or Senate versions of legislation reauthorizing surface transportation
programs may include elements of some or all of the provisions listed above. Such
provisions may serve to streamline the NEPA process for certain projects. For
reasons presented below, however, challenges to streamlining highway projects may
still exist.
Establishing a Statutory Environmental Review Process. Some
Members of Congress have expressed frustration that DOT has not promulgated
regulations to implement a coordinated environmental review process as required
under Section 1309 of TEA-21. In lieu of regulations, some Members of Congress
have expressed the desire to create such a process in statute. The inherent variability
among highway projects may make the creation of a single environmental review
process difficult to implement. The more significant a project’s environmental


57 “Interagency Guidance: Transportation Funding for Federal Agency Coordination,” is
available at [http://www.fhwa.dot.gov/environment/strmlng/igdocs/index.htm].

impacts, the more complicated the environmental review process will likely be for
any given highway project. Methods that are effective in streamlining one project
may not be as effective in another. For example, one project may require minimal
input from participating agencies, and hence little coordination among agencies,
while another project may require assistance from a variety of agencies in evaluating
impacts to certain resources or communities (e.g. minority neighborhoods or
endangered species habitat).
Considering this variability between projects, the establishment of provisions
applicable to all highway projects, such as the establishment of specific deadlines,
may be difficult to implement while remaining compliant with all applicable legal
requirements. Also, a participating agency may be required to provide consent to
allow certain activities to proceed (i.e., they may be required to issue permits for
certain activities) or to specify how certain impacts must be mitigated. Such actions
are required pursuant to separate statutory authority over which the FHWA has no
control. An environmental review process that allows for flexibility to respond to
these various legal requirements may allow for more efficient implementation of the
NEPA process.
Finally, any statutory changes that would result in changes to the way NEPA is
implemented would likely generate substantial attention from a variety of
stakeholders. If a coordinated environmental review process were implemented
through the regulatory process, the public and interested stakeholders would be
allowed to comment on the proposed process. Depended upon the changes
suggested, such a process may generate significant opposition among affected
stakeholders.
Establishing Lead Agency Authority. NEPA does not specify lead agency
authority. However, CEQ regulations implementing the NEPA process do specify
the authority and requirements applicable to both the lead agency and participating
agencies. In his capacity as the Chairman of the Interagency Transportation
Infrastructure Streamlining Task Force (see discussion regarding Executive Order
Implementation on page 26, above), Transportation Secretary Norman Mineta sought
guidance from CEQ Chairman James Connaughton regarding one element of agency
authority under current regulations. The Secretary asked for clarification regarding
the role of lead and cooperating agencies with regard to developing a highway58
project’s “purpose and need.” Secretary Mineta referred to the sometimes extended
interagency debates over purpose and need statements as a reason for delay in
highway project development.
In his response, Chairman Connaughton references current CEQ regulations
specifying that the lead agency has the authority for and responsibility to define the
a project’s purpose and need. Further, Chairman Connaughton referenced previous
federal court decisions giving deference to the lead agency in determining a project’s
purpose and need. While not addressed in this correspondence, CEQ regulations also


58 Text of Secretary Mineta’s May 6, 2003 letter, and Chairman Connaughton’s May 12,

2003 response, are available at [http://www.fhwa.dot.gov/stewardshipeo/minetamay6.htm].



specify the selection of reasonable alternatives as within the authority of the lead
agency.
The establishment of lead agency authority in law may serve to reassert this
authority to participating agencies. However, since this is a right already afforded
DOT under current regulations, it may not significantly streamline the NEPA
process.
Establishing a Statute of Limitations. It is generally the large, complex,
high-profile projects that would benefit the most from an efficiently coordinated
environmental review process. However, such large highway projects are also more
likely to generate public interest, and possibly public opposition. If members of the
public or a private interest group are adamantly opposed to a project, they may pursue
all possible legal recourse to stop or change it. NEPA, and the regulations
implementing it, currently contain no express provision for judicial review of agency
action, and hence, no deadline on petitions for review. The absence of such a
limitation has resulted, in some cases, in courts recognizing the statute of limitations
used for judicial review under the Administrative Procedure Act. That statute, 28
U.S.C. Section 2401, mandates broadly that civil actions against the United States
must be filed within six years after the right of action first accrues.
If a statute of limitations were established, there is no guarantee that special
interest groups would not file suit within the newly specified period of time.
However, establishment of a statute of limitations may streamline the NEPA process,
insofar as it would require judicial action to be taken earlier in the process, when
changes could be made more easily, as opposed to further along in the construction
process when changes may be more costly and take a greater amount of time to
address. Some environmental groups have argued that previously-suggested statutesth
of limitation (i.e., as specified in H.R. 5455, 107 Congress) were too restrictive and
may, in fact, lead to preemptive suits in an effort to preserve their right to sue.
Delegating Authority to States. One element of the NEPA process that has
been identified by some transportation stakeholders as a potential cause for delay is
the added step of obtaining FHWA approval of NEPA documentation. Some
transportation stakeholders argue that some federal environmental responsibilities
should be delegated to states. For example, AASHTO has asserted that project
review may be quickened if states were give the authority to process categorical
exclusions, meet endangered species requirements, meet historic preservation
requirements, meet wetlands requirements, and meet Section 4(f) requirements.59
Such stakeholders argue that delegation of such authority to the states could speed
up the environmental review process for highway projects by eliminating a
significant layer of bureaucracy that federal approval entails.
This approach is not endorsed by environmental stakeholders who have
expressed concern that the delegation of authority to the states would create a “fox
guarding the henhouse” scenario. They argue that if a state, which has a vested


59 “Delegation of Federal Environmental Responsibilities for Highway Projects,” prepared
for AASHTO by TransTech Management, Inc., April 2002.

interest in moving a project forward, is allowed to make certain determinations, those
determinations would not have the level of scrutiny that would be provided with
federal oversight.
One potential challenge to state delegation of authority includes a possible lack
of staff qualified to process potentially complex documentation. As discussed in the
May 2003 GAO report regarding stakeholders’ views on the time to conduct
environmental reviews, staff shortages have been identified by transportation
improvement stakeholders as a significant cause of highway project delays. If a state
does not have sufficient staff to accommodate its needs, the delegation of additional
authority to state or local transportation department staff may serve to slow the
NEPA process instead of streamline it. Staff at the state or local level may have
difficulty determining all environmental requirements applicable to their project
which could further slow the NEPA process if it takes longer to ensure that NEPA
documentation is complete. For example, it may be a difficult task for a highway
project sponsor to review and approve the documentation that will ultimately
demonstrate that all environmental requirements have been met. In the past, a state
may have had a consultant to prepare NEPA documentation for an EIS, but it may
have relied on FHWA oversight for more simple documentation, such as CE
determination documentation.
The issues above are not an exhaustive discussion of the challenges to
streamlining. They are also not likely to be factors in all projects. However, these
examples are intended to illustrate that there are many complexities inherent in the
NEPA process for highway projects.